With regard to the construction of the fighter squadron facilities in Cold Lake and Bagotville, as mentioned in paragraph 2.19 of the Auditor General of Canada's report titled “Delivering Canada's Future Fighter Jet Capability”: (a) what is the total amount spent on the construction of these facilities in Cold Lake and Bagotville to date; and (b) what are the details of all contracts, including (i) the start and end dates, (ii) the companies, (iii) the file number, (iv) the nature or description of the work, (v) the value of the contract, (vi) whether the contract was sole-sourced or awarded through a competitive bidding process?