Thank you very much for the question.
As it pertains to the excavation contract, Mr. Wright is correct. We have actually tendered and awarded the contract associated with what we call, or what you will commonly hear as, the mass excavation for the program. That represents the [Technical difficulty—Editor] in front of Centre Block. It does not represent the entirety of the excavation program. We still have to award the program that digs in and creates the connection between that parliamentary welcome centre and Centre Block.
For example, if you're looking at the cost table, you'll see that we are carrying $66 million associated with that excavation activity, and that is to carry out the fulsome budget that we're carrying to conduct both the excavation of the whole and the connections into Centre Block, in its totality. When we have the second aspect of the contract tendered, then we'll have actual costs for both elements of the program.
Result: 1 - 1 of 1

Show both languages
Refine Your Search
Discussed Topic
No match found
0
Person Speaking
No match found
0
Export As: XML CSV RSS

For more data options, please see Open Data