2.58 Conclusion – We found that overall progress on the department’s
efforts to place more attention on planning large IT projects, managing the
necessary transition, and involving all key stakeholders has been
unsatisfactory given that two of the four projects, the Global Case
Management System and the Expenditure Management Information System, have
significant governance issues (Exhibit 2.4).
Exhibit 2.4 - Recommendation 3.61 (from November 2006 Chapter 3
Large Information Technology Projects) : Government departments and agencies
should improve their external quality reviews of IT projects. Senior
departmental executives should review the key decision documents that are
produced to support the IT project and ensure the analysis is thorough and supportable before signing off the submission.
Progress – Satisfactory – IRC |
|
Progress
made on this recommendation was satisfactory for CRA (IRC). |
2.84 (formerly 2.85) Conclusion – The Secretariat has met its
commitments and developed and published business guidance to be used by
departments in preparing their business cases (see paragraph 2.26 and Exhibit
2.1) . However, we found that three of the five projects we examined in this
audit – GCMS, IRC, and Secure Channel – continue to have deficiencies
regarding identification and measurement of benefits (Exhibit 2.5).
2.85 (formerly 2.86) Recommendation – When departments and agencies
develop a business case, they should include a benefits measurement plan that
o contains
specific quantifiable benefits including clear benchmarks,
o assigns
responsibilities for delivering identified benefits, and
o includes a
process for measuring and reporting benefits. |
|
As noted in
the Agency’s response, work is ongoing in respect of measuring and reporting
on the benefits of IRC Phase 1 and includes target dates for the realization
of these benefits as follows:
- Technology
Transition to Business Processes – Ongoing through 2011/12
- Benefits
Measurement Cycle – Ongoing through 2012/13
- Benefits
Measurement Report – 2013/14
|
2.94 (formerly 2.95) Conclusion – We found that for three of the
four projects included in this portion of the audit, progress on improving
organizational capacity was satisfactory. EMIS did not access organizational
capacity as required (Exhibit 2.6).
Exhibit 2.6 – Recommendation 3.98 (from November 2006 Chapter 3
Large Information Technology Projects) :
At
the start of a project, departments and agencies should clearly demonstrate
that their organization is ready to accept the business transformation that
comes with the project and has the capability and commitment to successfully
deliver the project. Specifically, departments and agencies should analyze
their track record in
- completing
projects of similar size and complexity;
- completing
skills appraisals and plans to address shortfalls;
- planning
for business preparation, transition, and operational phases; and
- considering
key stakeholders buy-in and commitment.
Progress
- Satisfactory – IRC |
|
Progress
made on this recommendation was satisfactory for CRA (IRC). |
2.106 (formerly 2.107) Conclusion – We found that overall progress on
the implementation of risk management for the projects we reviewed has been
satisfactory, although progress is unsatisfactory for the Temporary Resident
Biometrics (Exhibit 2.7).
Exhibit 2.7 – Recommendation 3.111 (from November 2006 Chapter 3
Large Information Technology Projects) : Departments and agencies should
- comply
with the Treasury Board Secretariat project management guidance,
- closely
manage the project risks,
- monitor
key success factors, and
- regularly
report to management any significant internal or external event that may
prevent the expected project benefits or result in cost overruns or in
the project not being delivered on time.
Progress - Satisfactory – IRC |
Nil
response |
Progress
made on this recommendation was satisfactory for CRA (IRC). |